Question 256
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
Question 257
Who represents the three project interests on a project?
Question 258
Which process is used by a Team Manager to coordinate work on one or more of the project's products?
Question 259
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ?
] the project's plans
] the project's plans
Question 260
Which should be provided by corporate or programme management before the Starting up a Project process commences?