Question 241

Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
  • Question 242

    Which is a minimum requirement for applying the quality theme?
  • Question 243

    Which is a minimum requirement for applying the change theme?
  • Question 244

    Why is a Project Brief produced?
  • Question 245

    Which is a true statement about acceptance criteria?