Question 91

Which of the following take place before the initiation of a project?
1.Appoint the Executive
2.Capture requirements
3.Develop the Project Brief
4.Develop the detailed Business Case
  • Question 92

    Which is a purpose of a Risk Register?
  • Question 93

    Which should be funded by a change budget?
  • Question 94

    Which role is responsible for creating Checkpoint Reports?
  • Question 95

    Which is NOT a purpose of a Benefits Review Plan?