Question 111
Which does NOT reflect the PRINCE2 principle of continued business justification?
Question 112
What is the minimum number of management stages required by PRINCE2?
Question 113
Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.
Question 114
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
Question 115
Why is the 'initiating a project' process used?