Question 56
While preparing the Configuration Management Strategy, the Project Manager considered the options for
change control. He decided to recommend a change budget of E250k, but was undecided on the Change
Authority to recommend.
Which option is an appropriate Change Authority for the Outsourcing project?
change control. He decided to recommend a change budget of E250k, but was undecided on the Change
Authority to recommend.
Which option is an appropriate Change Authority for the Outsourcing project?
Question 57
The project is now closed. The expected increase in revenue is not being achieved. It has been agreed with the
team manager for the 'marketing materials' that additional marketing activities will be undertaken to achieve
the expected increase in revenue.
Who should be responsible for monitoring the results of the marketing activities, and why?
team manager for the 'marketing materials' that additional marketing activities will be undertaken to achieve
the expected increase in revenue.
Who should be responsible for monitoring the results of the marketing activities, and why?
Question 58
During the 'create the project plan' activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 3 products. Therefore, the project manager decides to wait until the end of stage 2 to assess the risks to the project plan.
Is this an appropriate application of the plans theme, and why?
Is this an appropriate application of the plans theme, and why?
Question 59
RISK
The following risk has been recorded:
"There may not be enough participants for the pilot courses to justify the continuation of the project." The recommended risk response is to improve the marketing campaign, and a risk budget exists to fund the response.
Here are three risk actions related to this response?
Which role (A-F) should be responsible for each action?
Choose only one role for each action. Each role can be used once, more than once, or not at all.

The following risk has been recorded:
"There may not be enough participants for the pilot courses to justify the continuation of the project." The recommended risk response is to improve the marketing campaign, and a risk budget exists to fund the response.
Here are three risk actions related to this response?
Which role (A-F) should be responsible for each action?
Choose only one role for each action. Each role can be used once, more than once, or not at all.

Question 60
Scenario
Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago.
She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed supplier assurance for this project?
Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago.
She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed supplier assurance for this project?
Premium Bundle
Newest PRINCE2-Practitioner Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PRINCE2-Practitioner Exam! BraindumpsPass.com now offer the updated PRINCE2-Practitioner exam dumps, the BraindumpsPass.com PRINCE2-Practitioner exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PRINCE2-Practitioner pdf dumps with Exam Engine here: