Question 76

The project is part of a program to develop more training courses that respond to new legislation. The project manager has requested that project support be made available from the program. As a result, the executive has confirmed that this will be carried out by the program office.
Is this appropriate, and why?
  • Question 77

    HOTSPOT
    Extract from the Project Product Description (with errors)

    The information in Column 1 may be entered in the Product Description for the chosen label design. Column 2 is a list of the quality headings (excluding Quality Method) in a Product Description. For each entry in Column 1 decide if it should be included in the Product Description headings shown and select the heading from Column 2 under which it should be recorded.
    Drop down the right answer

    Question 78

    Which of the following represents the four key characteristics a good Project board should display?
  • Question 79

    What will be the impact on the benefits?
  • Question 80

    MANAGING A STAGE BOUNDARY
    The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process.
    Which action should the project manager undertake as part of the 'update the business case' activity?