Question 11
Which three of the following are time-boxed events in Scrum? (Choose three.)
Question 12
When is it most appropriate for a Development Team to change the definition of "Done"?
Question 13
Why does the Product Owner want the Development Team to adhere to its definition of "Done"?
Question 14
During a Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum Master? (Choose two.)
Question 15
True or False: Every Scrum team must have a Product Owner and Scrum Master.