During the implementation of an item in the Sprint Backlog, a conflict arises between team members about what work is needed to make the item 'done'. Some say it is a part of the Definition of Done and others say it isn't. Steven, the Scrum Master, observes a debate forming and members beginning to take sides. What is the best action for Steven to take?
Correct Answer: C
The Scrum Master is a servant-leader for the Scrum Team. The Scrum Master helps the Scrum Team understand which of their interactions are helpful and which are not. The Scrum Master helps everyone change these interactions to maximize the value created by the Scrum Team.
Question 23
You are the Scrum Master for four teams working from the same Product Backlog. Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full time commitment from Phil, an external specialist. As the Scrum Master what should you do to solve this upcoming problem? (choose the best answer)
Correct Answer: C
Explanation As the Scrum Master, your role is to serve the Scrum Team by helping them to work effectively and deliver value. You are not responsible for managing the work or assigning tasks to the Developers. You should respect the self-organization and autonomy of the Developers, and support them in finding their own solutions to the problem. You should also facilitate collaboration and communication among the Developers and with other stakeholders, such as Phil and the Product Owner. Some reasons why the other options are not correct are: A: Preparing the Sprint Backlogs each day for the teams so Phil can spend some time in each team. This option is not correct because it violates the Scrum framework and the Scrum Master role. The Sprint Backlog is owned and managed by the Developers, not by the Scrum Master. The Scrum Master should not interfere with or dictate how the Developers plan and execute their work. The Scrum Master should also not impose a solution that may not be optimal or feasible for the teams or for Phil. B: Allocate Phil to one team per Sprint, so that over four Sprints every team will have had the support it requires. This option is not correct because it violates the Scrum framework and the Scrum Master role. The Scrum Master should not allocate resources or assign tasks to the teams or to Phil. The Scrum Master should also not impose a solution that may not be aligned with the Product Owner's priorities or the teams' needs. D: Ask Phil for a plan to hire and train additional people in his domain, and in the meantime work with the Product Owner and Developers to re-prioritize the work so that tasks not depending on Phil can be done first. This option is not correct because it violates the Scrum framework and the Scrum Master role. The Scrum Master should not ask Phil to do something that may be beyond his authority or responsibility. The Scrum Master should also not work with the Product Owner and Developers to re-prioritize the work, as this is the Product Owner's accountability. The Scrum Master should respect the Product Owner's decisions on what is valuable and what is not, and support the Developers in delivering that value. References: What is a Scrum Master? | Scrum.org What is a Sprint Backlog? | Scrum.org Who is responsible for dependency management? | Scrum.org [Managing Dependencies in Scrum - Scrum Alliance]
Question 24
Who must ensure that the work done for a Product Backlog item conforms to the Definition of "Done?"
Correct Answer: E
Explanation/Reference: Explanation: The Development Team owns the Definition of "Done" and is accountable for the quality of the Product Backlog items.
Question 25
You are a Scrum Master helping to establish five Scrum Teams that will be building a product. You discuss with them the high level of integration that the product Increment will require by the end of their first Sprint. It is a highly anticipated product, both by consumers and by the organization. Of the options raised by the future Scrum Team members, which option do you encourage? (Choose the best answer)
Correct Answer: D
The Scrum Guide states that "the moment a Product Backlog item meets the Definition of Done, an Increment is born" and that "the Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints". Therefore, to deliver a product Increment that is integrated and potentially releasable, all Scrum Teams must have a shared understanding of what "Done" means and ensure that their work meets that standard. This also enables transparency, inspection, and adaptation across the Scrum Teams.