Question 1
A program delivers incremental benefits, but is far from closure. The company completes an acquisition and defines new strategic objectives.
What should the program manager do next?
                        
                    
                    What should the program manager do next?
Question 2
After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000.
Based on this information, the program manager determines which of the following?
                        
                    
                    Based on this information, the program manager determines which of the following?
Question 3
What is the other name for critical delivery dates?
                        
                    
                    Question 4
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change. To whom should the change request be presented?
                        
                    
                    Question 5
An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review.
What should the program manager do next?
                        
                    
                    What should the program manager do next?
            