Question 46
Which two Resource Type roles offer the ability for routing to assign activities?
Question 47
A Company has a policy that "Gas Leak" and "Repair" Activity Types must be scheduled immediately to the nearest field resource.
In addition, the company needs to ensure that the system routes gas leaks with a higher priority than repairs.
What configuration must be used to support this requirement?
In addition, the company needs to ensure that the system routes gas leaks with a higher priority than repairs.
What configuration must be used to support this requirement?
Question 48
A company has a policy in which all of their technicians' working days will begin once they arrive at their first jobs, and end at the office depot after their last jobs.
Resource 'start' locations are set to their home addresses and 'end' locations are set to the office depot address.
What Resource Type settings ensure that routing will support this requirement?
Resource 'start' locations are set to their home addresses and 'end' locations are set to the office depot address.
What Resource Type settings ensure that routing will support this requirement?