Question 1

(You are the Contract Manager of the Employer ' s Representative in a Thermal Power Plant Project under FIDIC Silver Book (edition 2017). The Contractor submits two claims:
(1) USD 200,000 for additional costs due to an error in national piling standard NTS-PW-01 referenced in the Employer's Requirements.
(2) USD 300,000 for constructing an additional flood wall due to incorrect hydrological data in Site Data (water level miscalculated).
What is your determination for the Contractor?)
  • Question 2

    Before applying the procurement process of any FIDIC Book, the Employer should always check if there are local procurement rules that also apply. Which one of these responses is correct?
  • Question 3

    You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition
    2017). The project had been suspended due to a material change in the Employer ' s financial arrangement.
    You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?
  • Question 4

    Which two of the following statements are correct, regarding the Programme under FIDIC Red, Yellow and Silver Books (edition 2017)?
    Choose all of the correct answers (multiple possibilities).
  • Question 5

    Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?