Question 6

Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?
(Choose all correct answers - multiple possibilities)
  • Question 7

    Which two statements reflect an INCORRECT application of a Golden Principle?
  • Question 8

    (You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)
  • Question 9

    Which one of the following statements regarding drafting contracts based on FIDIC Books is correct?
  • Question 10

    A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months.
    This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?