Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?
Correct Answer: D
Comprehensive and Detailed Explanation: Option D is not a new procedure introduced in the 2017 FIDIC editions. The 2017 editions focus on dispute avoidance (A), quality management systems (B), and fair risk allocation (C), but do not explicitly require a Compliance Verification System as described. References: FIDIC Red, Yellow, Silver Books 2017 Editions - Overview of Changes FIDIC Contract Manager Study Guide, Module on Contract Updates
Question 12
In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions] Choose all of the correct answers (multiple possibilities).
Correct Answer: B,D
Comprehensive and Detailed Explanation: Option B is correct: When instructed to implement a Variation promptly, the Contractor must commence work and keep detailed records for subsequent valuation and impact assessment. Option D is correct: The Contractor is required to submit, within 28 days, a description, programme, and price proposal relating to the Variation as part of contract procedures. Option A is incorrect: The Contractor generally must proceed promptly regardless of dispute about foreseeability but may reserve rights via notices. Option C is incorrect: Safety cannot be compromised; the Contractor should not undertake hazardous work without mitigation. Option E is incorrect: The Contractor is generally bound to start work upon instruction even if the price is not yet agreed. References: FIDIC Red and Yellow Books 2017 Editions, Sub-Clause 3.5 - Variation Procedure FIDIC Contract Manager Study Guide, Module on Variations and Change Management
Question 13
Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
Correct Answer: A,B
Comprehensive and Detailed Explanation: Options A and B are correct: Both the Red and Yellow Books require the Engineer to certify payments before the Employer pays the Contractor. Option C (Silver Book) typically places the risk on the Contractor and often provides for payment without Engineer certification, reflecting the turnkey nature of the contract. References: FIDIC Red and Yellow Books 1999 & 2017 Editions, Clauses on Payment Certification FIDIC Silver Book 1999 & 2017 Editions - Payment Provisions FIDIC Contract Manager Study Guide, Module on Payment Procedures
Question 14
For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor's reporting requirement end?
Correct Answer: D
The Contractor's obligation to submit progress reports continues until all outstanding work identified in the Taking-Over Certificate has been completed. The Taking-Over Certificate signals substantial completion but may allow for outstanding minor works. Reporting is essential to monitor progress on these outstanding works. The Performance Certificate relates to final contract completion but reporting usually ends earlier only after all works are completed. Therefore, Option D is correct. References: FIDIC Red Book 1999 & 2017 Editions, Sub-Clause 4.21 - Progress Reports FIDIC Contract Manager Study Guide, Module on Communication and Reporting
Question 15
Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?
Correct Answer: A
Comprehensive and Detailed Explanation: Option A correctly reflects Golden Principles emphasizing the Employer's objective of obtaining value for money and the importance of avoiding disputes as much as possible. Other options either misrepresent the balanced nature of FIDIC principles or promote unfair or unbalanced positions. References: FIDIC Contract Management Guidelines - Golden Principles FIDIC Contract Manager Study Guide, Module on Legal and Ethical Considerations