Question 6

Do you need to consider bullet (ballistics) protection when designing a data center?
  • Question 7

    The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.
    Taking energy efficiency as the highest priority, which cooling system should you recommend?
  • Question 8

    A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.
    Are new floor loading calculations required?
  • Question 9

    You are allowed to use a calculator for this question.
    A computer room has a net volume of approximately 2,500 m³ / 88,287 ft³.
    The temperature is 20 °C / 68 °F.
    The required design concentration is 7%.
    The S-Factor is 0.1359 (metric) / 1.885 (imperial).
    Calculate the amount of gas required for this computer room based on FM200. What is the correct weight?
  • Question 10

    You need to determine the strategy for the cooling audit. All the servers are based on a front-to-rear (F-R) airflow design.
    Which location for the temperature/humidity measurement should you recommend for the audit?