Question 11

In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?
  • Question 12

    A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).
    Will the network architecture be part of this audit?
  • Question 13

    The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.
    What is the set-up in this data center?
  • Question 14

    What is the main disadvantage of using a ToR (Top of Rack) design?
  • Question 15

    You have three UPS systems connected in parallel. The UPS systems have an imbalance in the load sharing of approximately 20%.
    What should you recommend?