A luxury hotel project is in the design phase and is located on a scenic waterfront. It is one point away from attaining LEED Platinum certification. The LEED AP is recommending that the team pursue Innovation Credit, Innovation, Option 3. Additional Strategies. Which of the following credits would be desirable considering the location of the project?
Correct Answer: B
The LEED Platinum certification requires the project to achieve exemplary performance in at least one credit that allows it, as specified in the LEED Reference Guide1. One of the credits that meets this criterion is the Indoor Environmental Quality Credit, which focuses on providing healthy and comfortable indoor environments for occupants. The credit has two options: Quality Views and Enhanced Commissioning. Quality Views requires the project to have windows that provide views of natural scenery or water bodies, which can enhance the well-being and satisfaction of occupants. Enhanced Commissioning requires the project to have a comprehensive commissioning plan that ensures all systems are properly installed, tested, and operated before occupancy. Both options can help reduce energy consumption, improve indoor air quality, and create a positive sensory experience for occupants. Reference: LEED Reference Guide v4 LEED Platinum Certification - LD Products LEED Accreditation | LEED Certification & Credentials Overview - GBES
Question 42
The Required Breathing Zone Outdoor Airflow Vbz for a new banking facility is 0.120 CFM/ft2 (0.6 L/s/m2). If the team decides to attempt Increased Ventilation under Option 2 in the Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies, what is the minimum Design Zone Outdoor Airflow?
Correct Answer: A
This option requires the project to increase the breathing zone outdoor airflow by at least 20% above the minimum rates required by ASHRAE 62.1-2010. Therefore, the minimum design zone outdoor airflow is 0.120 CFM/ft2 x 1.2 = 0.144 CFM/ft2. References: = [LEED v4: Building Design + Construction Guide], [Indoor Environmental Quality Credit: Enhanced Indoor Air Quality Strategies], [ASHRAE 62.1-2010 User's Manual].
Question 43
Which is a benefit of earning Regional Priority credits?
Correct Answer: A
A benefit of earning Regional Priority credits is that the LEED project can achieve more sustainable outcomes by recognizing the issues that are a priority in the project's location. Regional Priority credits are not new LEED credits, but instead are existing credits that USGBC regional councils and chapters have designated as being particularly important for their areas1. The incentive to achieve the credits is in the form of a bonus point. If an RP base credit is earned, then a bonus point is awarded to the project's total points1. This way, the project can address the geographically specific environmental, social equity and public health priorities of its location2. References: * Regional priority credit lookup | U.S. Green Building Council * Regional Priority (RP) credits - U.S. Green Building Council
Question 44
When planning a water-efficient landscape design, the designer should consider including
Correct Answer: C
The best answer is C. native vegetation. This is because: * Native vegetation is adapted to the local climate and soil conditions, and therefore requires less water than non-native plants1. * Native vegetation also supports local biodiversity, reduces erosion, and enhances the aesthetic value of the landscape2. * Potable water is not a good option for water-efficient landscape design, as it is a scarce and valuable resource that should be conserved for human consumption and hygiene3. * Sprinkler systems are not a good option for water-efficient landscape design, as they can waste a lot of water through evaporation, runoff, and overspray4. Drip irrigation or micro-sprinklers are more efficient methods of watering plants. * Permeable pavement is not a good option for water-efficient landscape design, as it is not a plant-based element, but a hardscape feature that allows water to infiltrate into the ground. Permeable pavement can reduce stormwater runoff and pollution, but it does not directly contribute to water conservation in the landscape.
Question 45
A project team has installed a rainwater harvesting system on site. In which of the following could this system be recognized?
Correct Answer: C
A rainwater harvesting system on site could be recognized in the Sustainable Sites Credit, Rainwater Management and the Water Efficiency Credit, Indoor Water Use Reduction. The Sustainable Sites Credit, Rainwater Management rewards projects that reduce runoff volume and improve water quality by replicating the natural hydrology and water balance of the site1. A rainwater harvesting system can help achieve this by capturing and reusing rainwater on site2. The Water Efficiency Credit, Indoor Water Use Reduction rewards projects that reduce indoor water consumption by installing water-efficient fixtures and fittings3. A rainwater harvesting system can help achieve this by providing an alternative source of water for non-potable uses such as toilet flushing and irrigation4. The other options are not correct. The Water Efficiency Credit, Water Metering does not recognize rainwater harvesting systems, but rather requires projects to install permanent water meters that measure the total potable water use for the building and grounds. The Water Efficiency Prerequisite, Outdoor Water Use Reduction does not recognize rainwater harvesting systems, but rather requires projects to reduce outdoor water consumption by using plant species that are native or adapted to the region and by using irrigation systems that are efficient and properly controlled. The Water Efficiency Prerequisite, Indoor Water Use Reduction does not recognize rainwater harvesting systems, but rather requires projects to reduce indoor water consumption by 20% from the baseline by installing water-efficient fixtures and fittings. Reference: * Rainwater Management, p. 1 * NC-v4 SSc4: Rainwater management, p. 2 * Indoor water use reduction, p. 1 * NC-v4 WEc3: Indoor water use reduction, p. 3 * [Water metering], p. 1 * [Outdoor water use reduction], p. 1 * [Indoor water use reduction], p. 2
Newest LEED-AP-BD-C Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing LEED-AP-BD-C Exam! BraindumpsPass.com now offer the updated LEED-AP-BD-C exam dumps, the BraindumpsPass.com LEED-AP-BD-C exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com LEED-AP-BD-C pdf dumps with Exam Engine here: