A comprehensive rainwater management plan may include design elements such as
Correct Answer: B
Explanation These design elements are examples of low-impact development (LID) and green infrastructure (GI) practices that can reduce runoff volume and improve water quality by replicating the natural hydrology and water balance of the site1. Cisterns can collect and store rainwater for reuse or infiltration, porous pavement can allow water to seep into the ground, swales can convey and filter stormwater runoff, and vegetated roofs can reduce runoff and evapotranspiration2. References: = LEED v4: Building Design + Construction Guide, Achieving SSc Rainwater Management in LEED v4.1.
Question 17
A LEED Building Design and Construction: New Construction office building's HVAC system includes hot water from a central utility plant. The central utility plant is owned and operated by a management company. The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level Energy Metering, an energy meter must be installed for
Correct Answer: B
An energy meter must be installed for hot water at the main service point for the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level Energy Metering. According to the LEED v4 BD+C Reference Guide, this prerequisite requires that "all energy sources used by the building must be metered or submetered" 1. The hot water from the central utility plant is an energy source used by the building, even if it is not directly paid by the office. Therefore, it must be metered at the point where it enters the building. The other options are incorrect because natural gas is not an energy source used by the building in this case, and the flat fee or the ownership of the energy source do not exempt the project from the metering requirement. Reference: LEED v4 BD+C Reference Guide, Energy and Atmosphere Category, EAp Building-Level Energy Metering, page 569.
Question 18
Which of the following sinks is classified as a private lavatory faucet under Water Efficiency Credit, Indoor Water Use Reduction?
Correct Answer: C
Explanation A sink in a hotel room bathroom is classified as a private lavatory faucet under Water Efficiency Credit, Indoor Water Use Reduction.According to the LEED v4 BD+C Reference Guide, a private lavatory faucet is defined as "a faucet that is not generally accessible and is used only by the building's occupants and not by the public or visitors"1. A sink in an office restroom, a school classroom, or a shared office restroom are examples of public lavatory faucets, which have different baseline flow rates and requirements.References: LEED v4 BD+C Reference Guide, Water Efficiency Category, WEc Indoor Water Use Reduction, page 681.
Question 19
The project team has decided to substitute the flooring in the school gym with natural rubber flooring that has met the Sustainable Agriculture Standard. The cost of the substituted flooring is $80,000. The project will achieve
Correct Answer: A
Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices Natural rubber flooring is a bio-based material that can contribute to the achievement of Option 2 of the Sourcing of Raw Materials credit, which requires using products that meet at least one of the responsible extraction criteria for at least 25%, by cost, of the total value of permanently installed building products in the project1.By meeting the Sustainable Agriculture Standard (SAN), the natural rubber flooring demonstrates that it has been produced in a way that conserves biodiversity, protects natural resources, and enhances social and economic well-being2. Therefore, the cost of the substituted flooring ($80,000) can be counted towards the credit threshold. Reference Guide for Building Design and Construction v4 - Pages 263-2641 Sustainable Agriculture Standard | Rainforest Alliance3
Question 20
An owner has insisted on using a non-native or non-adapted plant species on both the vegetated roof and ground level. What Sustainable Sites credit will this decision impact the most?
Correct Answer: A
Using a non-native or non-adapted plant species on both the vegetated roof and ground level will impact the Sustainable Sites credit Site Development-Protect or Restore Habitat the most. This credit requires that at least 20% of the site area (excluding building footprint) or 5% of the site area (including building footprint) must be vegetated with native or adapted plants. Non-native or non-adapted plants do not qualify for this credit and may also have negative impacts on the local ecosystem and biodiversity. The other credits are not directly affected by the choice of plant species, although they may have other requirements related to vegetation, such as shading, reflectance, or lighting. Reference: LEED v4 BD+C Reference Guide, Sustainable Sites Category, SSc Site Development-Protect or Restore Habitat, page 648.
Newest LEED-AP-BD-C Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing LEED-AP-BD-C Exam! BraindumpsPass.com now offer the updated LEED-AP-BD-C exam dumps, the BraindumpsPass.com LEED-AP-BD-C exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com LEED-AP-BD-C pdf dumps with Exam Engine here: