According to the Integrative Process Credit, Integrative Process, the goal-setting workshop should identify
Correct Answer: C
According to the Integrative Process Credit, Integrative Process, the goal-setting workshop should identify targeted LEED credits. This is because the goal-setting workshop is a meeting that involves the project owner and key project team members to establish the project's sustainability goals, design objectives, and performance targets. One of the outcomes of the workshop is to identify the LEED credits that are relevant and achievable for the project, based on the project scope, budget, schedule, and site conditions. Therefore, option B is the correct answer. The other options are not the objectives of the goal-setting workshop. Potential project sites (option A) are usually determined before the goal-setting workshop, as they affect the project's feasibility and design. Expected water demand (option C) and expected energy demand (option D) are not identified in the goal-setting workshop, but rather in the preliminary water budget and the preliminary energy modeling, which are part of the analysis phase that follows the goal-setting workshop. For more information on the Integrative Process Credit, Integrative Process, you can refer to the LEED v4 Reference Guide for Building Design and Construction1 or the Projectific blog post on LEED Integrative Process Credit Explained2.
Question 22
What is the definition of the evapotranspiration rate?
Correct Answer: D
The evapotranspiration rate is the amount of water loss in a vegetated surface in units of water depth, such as millimeters or inches. It is a measure of the water demand of the plants and the climate conditions. It is used to calculate the baseline water use for irrigation in the Outdoor Water Use Reduction credit. Reference: * LEED v4 BD+C Reference Guide, page 5381 * Outdoor Water Use Reduction Credits in LEED v4 - HydroPoint2
Question 23
When working on a renovation project, asbestos containing materials have been found on the perimeter walls. When calculating the percentage of building being reused under the Materials and Resources Credit, Building Life-Cycle Impact Reduction, the materials remediated will be
Correct Answer: B
The Materials and Resources Credit, Building Life-Cycle Impact Reduction, rewards projects that reuse existing building structures and envelopes, or salvage materials from off-site or on-site sources. According to theLEED V5Reference Guide for Building Design and Construction, the project team must calculate the percentage of building being reused by dividing the area of the existing building structure and envelope that is reused by the total area of the completed building structure and envelope1. However, the project team must exclude from the calculation any hazardous materials that are remediated as a part of the project, such as asbestos, lead, mold, or PCBs1. Therefore, the asbestos containing materials found on the perimeter walls will be excluded from the calculation, regardless of the volume. References: * LEED V5Reference Guide for Building Design and Construction, Materials and Resources Credit: Building Life-Cycle Impact Reduction, page 5451 * Building life-cycle impact reduction | U.S. Green Building Council2
Question 24
Which of the following transit modes is considered to be walkable if it is within 1/2 mile (0.8 km) of the functional entry of a project?
Correct Answer: C
For Location and Transportation (LT) Credits: Access to Quality Transit, a local bus stop (C) within 1/2 mile (0.8 km) from a building's entrance qualifies as walkable transit. LEED defines walkable transit as options within reasonable distance for daily commuting, including bus stops, light rail stations, and streetcars. Taxi stands (A) aren't considered reliable public transit under LEED, and while streetcars (D) are valid, ferry terminals (B) are only acceptable within a 1-mile range.
Question 25
Which of the following strategies will aid in reducing indoor water use?
Correct Answer: D
According to the LEED v4: Building Design + Construction Guide, one of the strategies to reduce indoor water use is to optimize the consumption of showerheads by selecting fixtures that have a flow rate lower than the baseline of 2.0 gallons per minute (gpm) at 80 psi, or a local equivalent for projects outside the U.S. This can help the project achieve the Water Efficiency Prerequisite, Indoor Water Use Reduction, and the Water Efficiency Credit, Indoor Water Use Reduction, by reducing the aggregate water consumption from plumbing fixtures and fittings by at least 20% from the baseline1. The other choices are not strategies to reduce indoor water use, because: * Designing drip irrigation for landscape is a strategy to reduce outdoor water use, not indoor water use1. * Using high-efficiency HVAC systems is a strategy to reduce energy use, not water use, although it may have some indirect water savings by reducing the cooling tower water use2. * Excluding janitor closets in the building is not a feasible or practical strategy, as janitor closets are necessary for cleaning and maintenance purposes, and may also be required by codes or standards3.
Newest LEED-AP-BD-C Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing LEED-AP-BD-C Exam! BraindumpsPass.com now offer the updated LEED-AP-BD-C exam dumps, the BraindumpsPass.com LEED-AP-BD-C exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com LEED-AP-BD-C pdf dumps with Exam Engine here: