For an emergency care facility project, which of the following credits can be achieved if the total cost of permanently installed products are 25% cradle-to-cradle V3 Gold and 25% GreenScreen List Translator?
Correct Answer: C
The Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2. Material Ingredient Optimization & Innovation Credit, Innovation, Exemplary Performance can be achieved if the total cost of permanently installed products are 25% cradle-to-cradle V3 Gold and 25% GreenScreen List Translator. This is because these certifications indicate that the materials used in the project have been assessed for their environmental and health impacts, contributing to the achievement of these credits. Reference: LEED AP Building Design + Construction (LEED AP BD+C) V4 resources 1
Question 32
When required to measure residential and non-residential densities, Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 1. Surrounding Density requires project teams to measure the residential and non-residential densities in what way?
Correct Answer: A
For LEED BD+C Location and Transportation (LT) Credit: Surrounding Density and Diverse Uses, Option 1: Surrounding Density, the project team must measure: * Residential density in dwelling units per acre (DU/acre) or dwelling units per hectare (DU/ha). * Non-residential density based on floor area ratio (FAR). * The density must be measured within a ¼-mile (0.40 km) radius of the project boundary. This credit promotes high-density development and reduces urban sprawl, thereby improving access to amenities and public transportation. (Source: Official LEED BD+C Reference Manual)
Question 33
Which of the following are control measures recommended by the Sheet Metal and Air Conditioning National Contractors Association (SMACNA) for the Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan?
Correct Answer: A
Source control is one of the control measures recommended by the Sheet Metal and Air Conditioning National Contractors Association (SMACNA) for the Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan. Source control means minimizing the generation and emission of indoor air pollutants from the construction activities and materials. Some examples of source control are1: *Using low-emitting adhesives, sealants, paints, coatings, and flooring systems that comply with the VOC limits of the applicable LEED credit. *Storing absorptive materials in a protected area and covering them with plastic sheeting to prevent moisture and mold growth. *Scheduling the installation of finish materials after the completion of wet and dusty work, such as concrete pouring, drywall sanding, and painting. *Isolating work areas where high levels of contaminants are generated or used, such as welding, cutting, grinding, and solvent cleaning, and providing adequate ventilation and exhaust. *Prohibiting smoking, eating, and drinking in the work areas, and providing designated areas for these activities.
Question 34
A design team is pursuing Indoor Environmental Quality Credit, Indoor Air Quality Assessment. The building is 1,000 ft2 (93 m2) and has a 10 ft. (3 m) ceiling height. In order to earn the credit, what is the required volume of supply air for the entire building flush-out?
Correct Answer: C
According to the LEED Reference Guide for Building Design and Construction1, the Indoor Environmental Quality Credit, Indoor Air Quality Assessment, Option 1. Flush-Out requires the project to perform a building flush-out by supplying a total air volume of 14,000 cubic feet of outdoor air per square foot of gross floor area while maintaining an internal temperature of at least 60°F and no higher than 80°F and relative humidity no higher than 60%. The gross floor area of the building is 1,000 ft2 and the ceiling height is 10 ft, so the required volume of supply air for the entire building flush-out is: 14,000 ft3/sf x 1,000 sf = 14,000,000 ft3 References: * LEED Reference Guide for Building Design and Construction v4
Question 35
The current facilities requirements (CFR) and operations and maintenance plan (OMP) required for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification must include
Correct Answer: C
The current facilities requirements (CFR) and operations and maintenance plan (OMP) are two documents that are required for the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. The CFR is a document that describes the owner's project requirements, such as the design intent, performance goals, and operational needs of the building. The OMP is a document that provides information and guidance on how to operate and maintain the commissioned systems and equipment. According to the LEED v4 Reference Guide for Building Design and Construction, the CFR and OMP must include the minimum outside air requirements, which are the minimum rates of outdoor air ventilation that are needed to provide acceptable indoor air quality and thermal comfort for the occupants1. The issue logs, functional performance tests, and installation verification (construction) checklists are not required to be included in the CFR and OMP, but they are part of the commissioning process and documentation. References: *LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Prerequisite: Fundamental Commissioning and Verification, page 2611 *Fundamental commissioning and verification | U.S. Green Building Council2
Newest LEED-AP-BD-C Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing LEED-AP-BD-C Exam! BraindumpsPass.com now offer the updated LEED-AP-BD-C exam dumps, the BraindumpsPass.com LEED-AP-BD-C exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com LEED-AP-BD-C pdf dumps with Exam Engine here: