Question 56

The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendor's areas of poor performance?
  • Question 57

    The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
    Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)
  • Question 58

    A WBS is being developed for a project.
    Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
  • Question 59

    Which of the following is a characteristic of a project?
  • Question 60

    Which of the following describes a burn rate?