Question 76
A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present.
This review is referred to as:
This review is referred to as:
Question 77
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation?
(Choose two.)
Which of the following should the project manager bring to the meeting to support this recommendation?
(Choose two.)
Question 78
A risk with a high probability and medium consequence to a project has been identified. In response, the project manager has purchased an insurance plan with the intent to provide additional funds if the risk is realized. There is no risk to the schedule or scope. Which of the following types of risk strategies is this an example of?
Question 79
Which of the following defines a group of projects that work together to achieve a common goal?
Question 80
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?