Question 71
Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized?
Which of the following conflict resolution techniques has the project manager utilized?
Question 72
A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.
Which of the following terms describe this requirement?
Which of the following terms describe this requirement?
Question 73
A project manager learns that a key team member is required to work on a different assignment within the next two weeks. In which of the following organizational structures does the project manager work?
Question 74
Midway through a project, the building the team works in is destroyed by a hurricane. Which of the following types of communication is BEST in this event?
Question 75
The PMO is responsible for: (Choose two.)