Question 91
During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?
Question 92
Which of the following is a team-building stage that involves the team learning to trust one another's abilities and begin working together as a productive group?
Question 93
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
Which of the following techniques is the project manager using?
Which of the following techniques is the project manager using?
Question 94
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.
Which of the following should the project manager do NEXT?
Which of the following should the project manager do NEXT?
Question 95
A project manager is justifying a required change with the associated impact on the project.
Which of the following is the NEXT step?
Which of the following is the NEXT step?