Question 106
A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?
In which of the following documents can this information be found?
Question 107
The supervisor asks an engineer to be a project manager within the department. Of which of the following types of organizational structures is this an example?
Question 108
A project manager is attempting to establish the proper sequencing and duration of project activities.
Which of the following would be the MOST beneficial?
Which of the following would be the MOST beneficial?
Question 109
A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it.
Which of the following steps of the control was missed?
Which of the following steps of the control was missed?
Question 110
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?