Question 96

There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?
  • Question 97

    A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?
  • Question 98

    A project manager has developed the initial schedule for an upcoming project.

    Using the attached schedule, which of the following is the critical path?
  • Question 99

    Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
    Which of the following techniques is the project manager using?
  • Question 100

    A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.

    Which of the following is the NEXT appropriate step for the project manager to take?