Question 96
There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?
Question 97
A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?
Question 98
A project manager has developed the initial schedule for an upcoming project.

Using the attached schedule, which of the following is the critical path?

Using the attached schedule, which of the following is the critical path?
Question 99
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
Which of the following techniques is the project manager using?
Which of the following techniques is the project manager using?
Question 100
A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.

Which of the following is the NEXT appropriate step for the project manager to take?

Which of the following is the NEXT appropriate step for the project manager to take?