Question 111
Which of the following documents should be used to provide high-level reporting to key stakeholders?
Question 112
A project manager has received a change order that will reduce a project's timeline and budget. However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?
Question 113
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Question 114
Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below:

Which of the following is MOST likely the cause?

Which of the following is MOST likely the cause?
Question 115
A new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?