Question 1

Two team members have concluded that documentation is not required due to the size of the current project.
The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized?
  • Question 2

    Which of the following risk strategies prevents a risk from impacting a project?
  • Question 3

    Which of the following are characteristics of a project? (Choose two.)
  • Question 4

    While developing a project schedule, the project manager is attempting to sequence the following tasks:

    Which of the following is the correct sequence for the above tasks?
  • Question 5

    In a project with a BAC of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?