Question 6
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?
Which of the following documents should the project manager use to obtain this information?
Question 7
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items?
Which of the following documents would contain these items?
Question 8
A project manager needs to track the actual and estimated start and finish dates of all WBS work packages.
Which of the following is a necessary step to record the actual durations?
Which of the following is a necessary step to record the actual durations?
Question 9
A project manager is working on a large, complex project. While creating the project schedule, the project manager defines key points at which progress to date can be identified. Which of the following BEST describes the scheduling activity the project manager has completed?
Question 10
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
Which of the following techniques is the project manager using?