Question 16

A security breach was identified within a large company. The authentication server crashed, and employees are unable to access their accounts. Which of the following project constraints will MOST likely be impacted by this issue?
  • Question 17

    A mandatory evacuation has been ordered due to a natural disaster.
    Which of the following should be applied?
  • Question 18

    A risk with a high probability and medium consequence to a project has been identified. In response, the project manager has purchased an insurance plan with the intent to provide additional funds if the risk is realized. There is no risk to the schedule or scope. Which of the following types of risk strategies is this an example of?
  • Question 19

    A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?
  • Question 20

    A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.
    Which of the following techniques is MOST likely to be used to complete the project on time?