Question 41

During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer.
How should the team resolve this?
  • Question 42

    The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.
    What must the agile practitioner do?
  • Question 43

    The coach on a new agile team notices that one team member is influencing most of the team's decisions. What should the coach do?
  • Question 44

    Triple Nickels is a technique used in what kind of meeting?
  • Question 45

    Information transmission is greatest amongst team members who are working on: