Question 21

An earthquake occurs at the site of a manufacturing plant construction project. This affects the entire project budget.
What type of reserve analysis should the project manager consider?
  • Question 22

    A contract typically is used when a project is being performed for an external customer. An agreement is used as an input to______________
  • Question 23

    _____ is associated with a buyer's request for materials or equipment to meet a particular need or accomplish a specific purpose.
  • Question 24

    What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
  • Question 25

    You are using three point estimating technique to estimate the estimate of a scheduled activity. Which of the following statement are true given the following data:
    [Pessimistic=100 days] [Optimistic=40 days] [Most likely=65 days]Assuming a beta distribution you calculate that the duration average=66.6 days and duration variance=100.Assuming a triangular distribution you calculate that the duration average=68.33 days, and duration variance=151.38