Question 931

A product implementation project has a baseline schedule that indicates it should be complete wthin 30 days using three internal resources. As it nears completion, the Project manager learns that one resource has tell the project team. The sponsor approves hring an external resource at an additional cost.
To determine it the contingency reserve will be requited, what should the project manager calculate?
  • Question 932

    An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable lor many months What should the servant leader do?
  • Question 933

    For doing Quality Planning, you are going to use Design of Experiments to determine which factors might influence specific variables. What variable(s) can be used in your analysis?
  • Question 934

    A project manager receives a request for proposal (RFP) and must respond to the estimation section. The project manager is concerned that insufficient information is available to do the estimate.
    What method of estimation should the project manager use?
  • Question 935

    An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?