Question 6

The estimate costs process uses all the following tools and techniques EXCEPT______________
  • Question 7

    Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
  • Question 8

    A customer initiated a minor scope change and expects this to be completed without delays or additional costs. The project manager believes that they have adequate authorization to make the decision themselves but is not quite sure.
    What should the project manager do next?
  • Question 9

    On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client.
    The project manager is now in the initial stage of a new project with the same subcontractors and client.
    How should the project manager set up communications?
  • Question 10

    A project team has been together for a long time and has been led by three different project managers. Lately, the performance of one of the team members has been declining and has affected the project delivery.
    What should the current project manager do to ensure that team performance is improved and sustained?