Question 11

A project manager is working on a software implementation project for which a well-defined change management plan is in place During project execution a software developer notices that an untested and unapproved security patch needs to be installed or the system will become unstable What should the project manager do?
  • Question 12

    The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
  • Question 13

    A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
    In which project document should the project manager record the concern?
  • Question 14

    A project manager is assigned to a new marketing campaign. The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables, and stakeholders. The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.
    What should the project manager do?
  • Question 15

    A new quality report was distributed to stakeholders after the sponsor approved it. A senior manager requests changing the colors and sizes of some of the graphs included in the report.
    What should the project manager do?