Question 31

Whose interests are specifically represented by the senior supplier?
1. Those ensuring the project is value for money.
2. Those who will use the project's products.
3. Those who will be developing the project's products.
4. Those responsible for the project's technical integrity.
  • Question 32

    Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?
  • Question 33

    Which TWO statements about the supplier subject matter expert are CORRECT?
    1) They provide a wider picture of the customer view.
    2) They prioritize requirements at the detailed level.
    3) They should be focused on the customer.
    4) They ensure that the work is compliant with project standards.