Question 81
When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
Question 82
Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces).
Question 83
Which best describes the Product Backlog?
Question 84
The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.
Question 85
Where are two good ways for the Development Team to make non-functional requirements visible?
(Choose two.)
(Choose two.)