Question 31
Paul is a Product Owner for multiple products. Each product is allocated a dedicated Scrum Team and a set budget. Based on the average velocity of a previous product release, Paul had estimated a new product to take
9 Sprints to complete. The average velocity of the previous product release was 50 completed units of work per Sprint. Over the first 3 Sprints, the Development Team reported an average velocity of 40 completed units per Sprint, while not fully completing the required integration tests. The Development Team estimates that integration testing would require additional effort to make the increments shippable. The Development Team is unsure if the required velocity is achievable.
What is the most effective way to recover?
9 Sprints to complete. The average velocity of the previous product release was 50 completed units of work per Sprint. Over the first 3 Sprints, the Development Team reported an average velocity of 40 completed units per Sprint, while not fully completing the required integration tests. The Development Team estimates that integration testing would require additional effort to make the increments shippable. The Development Team is unsure if the required velocity is achievable.
What is the most effective way to recover?
Question 32
Who manages the progress of work during a Sprint?
Question 33
Which stakeholder is the most important for the Product Owner to satisfy?
Question 34
Scrum has a role called "Project Manager."
Question 35
Steven is a Scrum Master on a new Scrum Team.
What would be the best way for him to determine if the Product Owner is interacting enough with the Development Team during a Sprint?
What would be the best way for him to determine if the Product Owner is interacting enough with the Development Team during a Sprint?