Question 91
A non-profit organization launched a program to reduce its dependence on regularly decreasing government funding sources. This program's goal was (o raise 50 percent of its operating expenses by selling its services to the for-profit sector. After three years, the goal was reached, deemed complete, and transitioned to operations.
Eighteen months later, the organization discovers that its dependence on government funds has now increased to 80 percent, even though its operating budget has largely stayed the same What should the program manager have done to avoid the issue of program benefits being unrealized after more than a year of implementation?
Eighteen months later, the organization discovers that its dependence on government funds has now increased to 80 percent, even though its operating budget has largely stayed the same What should the program manager have done to avoid the issue of program benefits being unrealized after more than a year of implementation?
Question 92
Identify the core switch(es) and server(s) of the data center in the diagram below by dragging the appropriate term into each box in the diagram.


Question 93
Communicating a project's design and technical specifications to the client and stakeholders is part of the
___________of the project.
___________of the project.
Question 94
A global financial system is being delivered by the program learn to allow access from anywhere in the world Following a new cross-border regulation applying to privacy of local banking data accessed from abroad, the CEO of the bank requests that an external audit be conducted lo validate compliance with this new regulation.
This event, which was not anticipated al this phase of the program, will generate additional work tor the program learn. This effort Is not included in the current program roadmap and benefits delivery plan What immediate actions should the program manager take?
This event, which was not anticipated al this phase of the program, will generate additional work tor the program learn. This effort Is not included in the current program roadmap and benefits delivery plan What immediate actions should the program manager take?
Question 95
The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?