Question 96

During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and
  • Question 97

    A program manager learns that their company's organizational strategy has changed This change impacts one component project of a program misaligning it with both the program objectives and the new organizational strategy This component project, however, is already 90 percent complete.
    What should the program manager do next?
  • Question 98

    Open RFI's should be reviewed on a _________basis.
  • Question 99

    What is the MAXIMUM number of work areas served by a single Multiuser Telecommunications Outlet Assembly (MUTOA)?
  • Question 100

    A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end What should be completed first to close all appropriate contracts?