Question 41
You are the Test Manager of a new project aimed at developing a software system that
must be certified at level B of the DO-178B standard. The project will follow a V-Model
software development life cycle and it will have four formal levels of testing: component,
integration, system and acceptance testing.
You must produce the test plan documentation for this project by providing an adequate
coordination across the four levels of testing in order to assure audit ability.
Which of the following answers would you expect to best describe how to organize the test
plan?
K3 2 credits
must be certified at level B of the DO-178B standard. The project will follow a V-Model
software development life cycle and it will have four formal levels of testing: component,
integration, system and acceptance testing.
You must produce the test plan documentation for this project by providing an adequate
coordination across the four levels of testing in order to assure audit ability.
Which of the following answers would you expect to best describe how to organize the test
plan?
K3 2 credits
Question 42
Which of the following would you expect to be most likely an example of a motivating factor
for testers?
K2 1 credit
for testers?
K2 1 credit
Question 43
Which of the Mowing should be used to understand the context of testing within an organization?
Question 44
Consider an information system of a Pay-Tv company based on a SOA architecture.
The integrated system currently consists of three core systems:
- a CRM (Customer Relationship Management) system
- a BRM (Billing and Revenue Management) system
- a CAS (Conditional Access System) system all of them communicating with SOA Middleware.
You have been asked to manage the testing activities for the integration of two additional off-the-shelf systems from two different vendors: a SMS (Short Message Service) server and an IVR (Interactive Voice Response) system.
Assume that there is a high likelihood that the two off-the-shelf systems will be low-quality and that you have a clear proof that the testing performed by the two vendors on their systems has been unsystematic and unprofessional. This obviously leads to higher quality risk for the overall integrated system.
You are the Test Manager of this project. Your main goal is to plan for testing activities to mitigate this risk.
Which of the following answers best describes the test activities (assuming it is possible to perform all of them) you should plan for?
The integrated system currently consists of three core systems:
- a CRM (Customer Relationship Management) system
- a BRM (Billing and Revenue Management) system
- a CAS (Conditional Access System) system all of them communicating with SOA Middleware.
You have been asked to manage the testing activities for the integration of two additional off-the-shelf systems from two different vendors: a SMS (Short Message Service) server and an IVR (Interactive Voice Response) system.
Assume that there is a high likelihood that the two off-the-shelf systems will be low-quality and that you have a clear proof that the testing performed by the two vendors on their systems has been unsystematic and unprofessional. This obviously leads to higher quality risk for the overall integrated system.
You are the Test Manager of this project. Your main goal is to plan for testing activities to mitigate this risk.
Which of the following answers best describes the test activities (assuming it is possible to perform all of them) you should plan for?
Question 45
Which of the following would you expect to be most likely an example of a motivating factor for testers?