Question 11

During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
  • Question 12

    If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using
  • Question 13

    Is activity 7001 pictured correctly in the precedence diagram?
  • Question 14

    You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?
  • Question 15

    The amount of time that an activity can be delayed from its early start date without delaying project completion is called