Question 16

Identify the minimum project duration.
  • Question 17

    Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that
  • Question 18

    Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
  • Question 19

    Which of the following is NOT required when performing weekly or monthly schedule updates?
  • Question 20

    Total float is defined as the amount of time an activity can be delayed without impacting