Question 21

Which of the following are NOT considerations or constraints of the planning process for construction scheduling?
  • Question 22

    A driving relationship is _____________________.
  • Question 23

    Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
  • Question 24

    Determine the correct formula and date for the late finish for Activity 9004.
  • Question 25

    How much Total Float does drafting the product manual have?