Question 26

What was the original planned duration for Activity A through Activity G?
  • Question 27

    Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
  • Question 28

    Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
  • Question 29

    Determine the correct formula and date for the late finish for Activity 2002.
  • Question 30

    All the following describe the critical path of a schedule EXCEPT: