Question 31
In its simplest form, what is the main drawback of critical path method scheduling?
Question 32
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
Question 33
What is the workweek period for this project?


Question 34
Which of the following is NOT a tool or technique used to perform scope planning?
Question 35
What method offers the best chance of the schedule being used effectively to implement the project in the field?