Question 31
When considering risks, which describes an opportunity in a project?
Question 32
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
Question 33
Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?
Question 34
The application of which principle helps to define what should be included in a project?
Question 35
How does the 'managing product delivery' process ensure that the team manager's perspective is provided in a work package?